SUMMARY
PROCESS
The R407C contained within the existing chiller was decanted into suitable recovery cylinders and taken away to a refrigerant recycling plant. 3 Phase power was decommissioned temporarily as well as ancillary & control feeds. The mechanical chilled water flow and return connections were disconnected & pipework stripped back to be reconfigured at a later date. Climate chiller was physically removed from its base ready for removal via crane.
London Direct Commercial appointed preferred lifting contractor Danny Laidlaw and Sons to oversee the chiller exchange at roof level. Lifting plans and drawings were provided and the ground was checked for suitability in advance of the planned lift. Firstly the existing Climate chiller was lifted from its position to ground level, and other redundant pipework followed.
New galvanised beams supplied by LDC were lifted into place and fixed before the new chilled along with AV mountings was lifted and positioned accordingly. This work took place outside of normal working hours on Saturday morning.
A new primary chilled water flow pump set was installed in the basement, as well as a VEXO X-Pot for maximum filtration and system dosing.